Current:Home > MyVibrations in cooling system mean new Georgia nuclear reactor will again be delayed -Finovate
Vibrations in cooling system mean new Georgia nuclear reactor will again be delayed
EchoSense View
Date:2025-04-07 19:40:55
ATLANTA (AP) — Georgia Power Co. said Thursday that vibrations found in a cooling system of its second new nuclear reactor will delay when the unit begins generating power.
Plant Vogtle’s Unit 4 now will not start commercial operation until sometime in the second quarter of 2024, or between April 1 and June 30, the largest subsidiary of Atlanta-based Southern Co. announced.
The utility said in a filing to investors that the vibrations “were similar in nature” to those experienced during startup testing for Unit 3, which began commercial operations last summer, joining two older reactors that have stood on the site near Augusta for decades
In that case, the utility found that a pipe vibrated during testing because construction workers hadn’t installed enough bracing. Georgia Power said the Unit 4 problem has already been fixed but too much testing remains to be done to make the March 30 deadline.
Georgia Power said it’s likely to lose $30 million in profit for each month beyond March that Unit 4 isn’t running because of an earlier order by state utility regulators. The five members of the Georgia Public Service Commission ordered that the company can’t earn an additional return on equity through a construction surcharge levied on Georgia Power’s 2.7 million customers after March 30.
The typical residential customer has paid about $1,000 in surcharges over time to pay for financing costs.
The company said its construction budget won’t be affected if Unit 4 starts by June 30 but it would have to pay $15 million a month in extra construction costs if the project extends into July.
Regulators in December approved an additional 6% rate increase to pay for $7.56 billion in remaining costs at Vogtle, expected to cost the typical residential customer $8.95 a month. That’s on top of the $5.42 increase that took effect when Unit 3 began operating.
The new Vogtle reactors are currently projected to cost Georgia Power and three other owners $31 billion, according to calulations by The Associated Press. Add in $3.7 billion that original contractor Westinghouse paid Vogtle owners to walk away from construction, and the total nears $35 billion.
The reactors were originally projected to cost $14 billion and be completed by 2017.
Units 3 and 4 are the first new American reactors built from scratch in decades. Each can power 500,000 homes and businesses without releasing any carbon. But even as government officials and some utilities are again looking to nuclear power to alleviate climate change, the cost of Vogtle could discourage utilities from pursuing nuclear power.
Georgia Power owns 45.7% of the reactors, with smaller shares owned by Oglethorpe Power Corp., which provides electricity to member-owned cooperatives; the Municipal Electric Authority of Georgia; and the city of Dalton.
Some Florida and Alabama utilities have also contracted to buy Vogtle’s power.
veryGood! (88)
Related
- Stamford Road collision sends motorcyclist flying; driver arrested
- South Dakota Gov. Kristi Noem banned from tribal land over U.S.-Mexico border comments: Blatant disrespect
- Connecticut remains No.1, while Kansas surges up the USA TODAY Sports men's basketball poll
- First Russians are fined or jailed over rainbow-colored items after LGBTQ+ ‘movement’ is outlawed
- Cincinnati Bengals quarterback Joe Burrow owns a $3 million Batmobile Tumbler
- Sailor missing more than 2 weeks arrives in Hawaii, Coast Guard says
- When is Super Bowl halftime show? Here's when you should expect to tune in to watch Usher
- Prince William likely to step up amid King Charles III's cancer diagnosis, experts say
- Paula Abdul settles lawsuit with former 'So You Think You Can Dance' co
- Bob Beckwith, FDNY firefighter in iconic 9/11 photo with President George W. Bush, dies at 91
Ranking
- Stamford Road collision sends motorcyclist flying; driver arrested
- Executive Producer of Eras Tour, Baz Halpin, is mastermind behind Vegas Show 'Awakening'
- Applebee's makes more Date Night Passes available, but there's a catch
- Tennessee governor pitches school voucher expansion as state revenues stagnate
- Small twin
- Delays. Processing errors. FAFSA can be a nightmare. The Dept. of Education is stepping in
- Less rain forecast but historic Southern California storm still threatens flooding and landslides
- Patrick Mahomes at Super Bowl Opening Night: I'd play basketball just like Steph Curry
Recommendation
DoorDash steps up driver ID checks after traffic safety complaints
Executive Producer of Eras Tour, Baz Halpin, is mastermind behind Vegas Show 'Awakening'
A total solar eclipse will darken U.S. skies in April 2024. Here's what to know about the rare event.
Senegal's President Macky Sall postpones national election indefinitely
Woman dies after Singapore family of 3 gets into accident in Taiwan
A famous climate scientist is in court, with big stakes for attacks on science
When is Super Bowl halftime show? Here's when you should expect to tune in to watch Usher
'Cozy cardio': What to know about the online fitness trend that's meant to be stress-free