Another Pipeline Blocked for Failure to Consider Climate Emissions
View
Date:2025-04-16 14:58:49
[UPDATE: On Sept. 15, FERC overrode New York’s decision on the Valley Lateral Project, stating that New York officials had missed a deadline to act. Bloomberg BNA discusses that move and the likelihood that the state will appeal, here.]
It might be getting harder to win approval for new fossil fuel projects without first examining their impacts on climate change. Last week, regulators in New York rejected key permits for a natural gas pipeline, saying a previous federal approval had failed to consider the resulting greenhouse gas emissions.
The pipeline in question, the 7.8 mile-long Valley Lateral Project, would supply a 680 megawatt power plant that’s currently under construction. The pipeline had already received approval from the Federal Energy Regulatory Commission (FERC), but because it crosses several streams and wetlands, it needed state regulators to sign off, too.
In a letter to FERC on Aug. 30, Thomas Berkman, deputy commissioner and general counsel at the New York Department of Environmental Conservation, wrote that federal regulators had “failed to consider or quantify the indirect effects” of the emissions produced when the fuel shipped through the pipeline is eventually burned.
The state cited a federal court ruling issued just one week earlier as its justification for denying the permits. In that case, a federal circuit court in Washington, D.C., rejected an approval by FERC of a separate pipeline in the Southeast, saying “FERC must either quantify and consider the project’s downstream carbon emissions or explain in more detail why it cannot do so.”
Berkman wrote that that court decision constitutes “a material change in applicable law” and that the commission should therefore reexamine the Valley Lateral application.
Other Fossil Fuel Projects Blocked
Courts or regulators have blocked fossil fuel projects several times in the past month, at least in part because federal agencies failed to account for downstream climate emissions. On Aug. 14, a federal district judge in Montana rejected a proposed expansion of a coal mine in that state, saying the U.S. Department of Interior hadn’t adequately considered climate and other impacts.
New York’s denial of the permit is the latest in a series of decisions by Gov. Andrew Cuomo’s administration to block natural gas projects since he banned hydraulic fracturing in the state in 2014. In April, the state denied permits for a proposed pipeline from Pennsylvania’s gas fields. A year earlier, it blocked another interstate pipeline. In both cases, the projects had received federal approval but required the same type of permits from the state under the Clean Water Act.
In this case, however, the state did not actually rule on the water permits themselves, but instead sent the case back to FERC to review the climate impacts.
Challenging the Pipeline Boom
“I don’t know why the DEC chose this procedural argument,” said Pramilla Malick, of the local advocacy group Protect Orange County. “Ultimately, the DEC has a legal and moral authority to protect water quality” and deny the permits outright, she said. “They have basically kicked it to FERC.”
Malick’s group has been fighting a buildout of natural gas infrastructure in New York’s Orange County since 2011, and she said the state’s previous approvals of the CPV Valley Energy Center, the power plant that would be supplied by the Valley Lateral pipeline, were contrary to Cuomo’s climate policies and his rejection of fracking.
The plant is also at the center of corruption charges that were brought by federal prosecutors last year against two Cuomo aides. One of the aides, Joseph Percoco, is charged with taking bribes from Competitive Power Ventures, the company behind the plant, while a former company official is also named as a defendant. The case has yet to go to trial.
The opposition to the pipeline and the power plant has drawn support from national environmental groups and advocates, including Bill McKibben, who attended a rally in August. They’ve argued that the power plant would substantially increase the state’s greenhouse gas emissions, and they called on the state to reject the pipeline as a way to stop the plant.
Michelle Hook, a spokeswoman for Millennium Pipeline Company, which proposed the Valley Lateral Project, said in a statement that the state’s ruling “does not appear to be a clear-cut decision and our lawyers are reviewing it to determine how to proceed,” adding “the agency’s issue is with the power plant’s greenhouse gas emissions and not any direct environmental impact of our pipeline.”
Competitive Power Ventures, the company building the power plant that was to burn the gas shipped through the Valley Lateral line, told the Times Herald-Record last week that the company would proceed with its plans to finish the plant and called the state’s decision “without merit.”
Wider Implications?
It’s unclear whether the latest developments will affect another project—a proposed expansion of a gas storage facility in New York’s Finger Lakes region—that’s awaiting state approval and has also prompted a vibrant grassroots opposition.
The original proposal would have increased capacity at an existing natural gas storage facility and added storage of liquefied petroleum gas. While the natural gas piece of the project received federal approval in 2014, it spurred a years-long civil disobedience campaign and construction never began.
In May, the company behind the project announced it was abandoning the natural gas portion because it couldn’t secure enough contracts from customers. The liquefied gas piece, however, is overseen by the state, which has not yet issued a ruling. In lobbying against the project, opponents have cited its impacts on water and climate change.
veryGood! (1)
Related
- Toyota to invest $922 million to build a new paint facility at its Kentucky complex
- Kentucky’s former attorney general Daniel Cameron to help lead conservative group 1792 Exchange
- T.I., Tiny Harris face sexual assault lawsuit for alleged 2005 LA hotel incident: Reports
- The USS Gerald R. Ford aircraft carrier is returning home after extended deployment defending Israel
- Meet first time Grammy nominee Charley Crockett
- How to watch the Golden Globes: Your guide to nominations, time, host and more
- Kentucky’s former attorney general Daniel Cameron to help lead conservative group 1792 Exchange
- Michigan detectives interview convicted murderer before his death, looking into unsolved slayings
- Off the Grid: Sally breaks down USA TODAY's daily crossword puzzle, Triathlon
- How much is the child tax credit for 2023? Here's what you need to know about qualifying.
Ranking
- Which apps offer encrypted messaging? How to switch and what to know after feds’ warning
- Golden Bachelor's Leslie Fhima Hospitalized on Her 65th Birthday
- Retirees set to earn up to $4,873 starting this month: What to know about 2024 Social Security benefits
- Japan police arrest a knife-wielding woman inside a train after 4 people are reported injured
- Selena Gomez engaged to Benny Blanco after 1 year together: 'Forever begins now'
- South Korea views the young daughter of North Korean leader Kim Jong Un as his likely successor
- Illinois juvenile justice chief to take over troubled child-services agency
- A 13-year-old in Oklahoma may have just become the 1st person to ever beat Tetris
Recommendation
Newly elected West Virginia lawmaker arrested and accused of making terroristic threats
A hiker is rescued after falling down an Adirondack mountain peak on a wet, wintry night
Democratic Gov. Andy Beshear calls for unity in GOP-leaning Kentucky to uplift economy, education
One attack, two interpretations: Biden and Trump both make the Jan. 6 riot a political rallying cry
Bodycam footage shows high
Founder of retirement thoroughbred farm in Kentucky announces he’s handing over reins to successor
What does cost of living mean? How we calculate the comparison for states and cities.
Two large offshore wind sites are sending power to the US grid for the first time